The Sydney Waterfront Campus is taking shape and checking off major progress this month as construction continues. Having reached 98 per cent of tenders being awarded, the build is expected to welcome 200 workers daily on site in the coming months – an increase from 175.
The latest progress
- Building B West glazing began arriving this month, the last major portion of glazing to be installed. Some of the largest pieces of glazing are currently underway, marking a milestone in the build once complete
- Drywall is being installed in all buildings
- The final two elevators are under installation
- All major equipment is in place in the main mechanical room and installation is underway
We thank you for your patience and understanding as we complete these important phases of our construction build.
Related Stories

Read about the student housing construction progress being made at Akerley Campus.

Read about the construction progress being made at Akerley. Ivany, Pictou and Sydney Waterfront Campus.