Sydney Waterfront Campus | October 2023
Category:
Construction updates

In less than one year, Sydney Waterfront Campus will open its doors to students. After a busy fall of construction progress, the new campus remains on schedule for September 2024.

Here's a sneak peak of the inside of NSCC's bright, new campus.
The latest progress:
- Building C East Apolic panel installation ongoing
- Hard tile/LVT and carpet tile installation continues
- The parking lot is paved and site trailers are now moved to be able to start construction on the new retaining wall
- Geothermal rejection wells are drilled with final testing to begin in early November
- Mechanical and electrical rough ins continue on scheduleAtrium glazing is now installed
- Fire damper testing continues
- Mechanical piping flushing and cleaning has started
- Final above ceiling inspections have begun on BL4&5
- Power to BL4&5 will begin in mid-November for heat pump testing
We thank you for your patience and understanding as we complete these important phases of this project.
Related Stories

Read about the construction progress being made at NSCC's newest campus.

Read about the construction progress being made at NSCC's newest campus.