Views from the fifth floor of the soon to be student housing at Ivany Campus.
The student housing project at Ivany Campus is starting to take shape and look significantly different as exterior work continues ahead of the winter months.
The latest progress:
- Installation of exterior wall panels has started and will be completed by the end of December
- Fireproofing of steel framing continues
- Plumbers are installing main plumbing infrastructure
- Electricians are installing main electrical infrastructure
- Roofing membrane installation has started
We thank you for your patience and understanding as we complete these important phases of this project.