Ivany Campus | August 2023

A drone shows an overhead view of a steel building structure.

The month of August brought important progress to Ivany Campus’ student housing construction site, as crews work towards its 2025 opening date.

 A construction site is shown of a new student housing facility being built.
The building's steel framing is expected to be complete by the end of September.

The latest progress:

  • Steel framing is nearing completion as the third and final section is under assembly. Steel framing is expected to be complete by the end of September
  • Concrete floors are currently being poured
  • Plumbing and electrical services have begun
  • All retaining walls are now complete. Temporary guard rails are presently in place
  • Exterior walls of the building (precast wall panels) are scheduled to begin in mid-October
  • Windows are scheduled to be delivered in mid-November

We thank you for your patience and understanding as we complete these important phases of this project.

Related Stories

A construction site shows the steel structure in place of a new building. Ivany Campus | July 2023

Read about the student housing construction progress being made at Ivany Campus.

Image shows a construction zone being prepped for a large student housing build. Ivany Campus | June 13-16

Read about the student housing construction progress being made at Ivany Campus.

Top